Premises London SW1
Size 8,000 sq.ft.
Timescale 8 weeks

Leonard Cheshire Foundation

Scope of works included

  • Partitioning
  • Air conditioning upgrade
  • Decoration
  • Signage
  • Special disabled facilities
  • Hearing aid loop in conference room
  • Voice enhancement system
  • IT & communications
  • Reconfiguration of layout
  • Storage wall facilities
  • Furniture

Client comment

David Kay, Director of Finance & Administration at Leonard Cheshire commented: 

"I would like to congratulate Maris on their efficiency and tidiness whilst on site. Not only did they leave no mess, but amazingly, completed the project in a far shorter time than was initially quoted. All in all we were very pleased with the end result."